| Excavation |
A
concrete tank would obstruct the running water, if an
unexpected flooding occurred.
|
Aeration of the Entire Cross Section
|
Depending
on the concentration of BOD, the aeration quantity changes,
however, the aeration is always done over the entire cross
section. A sludge removal is unnecessary. Inorganic matter
in the river water is always outflowed. Water blowers
are used so that a control tower is unnecessary.
|
| Sludge Removal and Sludge Treatment |
Unnecessary.
|
Denitrification
|
Starts happening.
|
Water Gathering Facility
|
Should
be built with soil-sand-proofs and garbage-proofs.
|
Specifications
|
BOD: Below 20mg/l
|
Actual Retention Time: 0.5h
Aeration: 0.5m3/m2・h
Flow-Down Distance: 5m |
BOD: Over 30mg/l
|
Actual Retention Time: Over 1.0h
Aeration: Over 1m3/m2・h
Flow-Down Distance: 10-15m |